Question: Let's say we have a project with two tasks, building a fence and laying sod. The initial cost baseline is: Determine the percent complete for

 Let's say we have a project with two tasks, building a

fence and laying sod. The initial cost baseline is: Determine the percent

Let's say we have a project with two tasks, building a fence and laying sod. The initial cost baseline is: Determine the percent complete for task of building the fence. 10%75%15%50% Using the information given to you in Question 5, determine the Earned value (EV) for the task of laying sod. $30$300$3000$800