Question: Loans are evaluated in a process with two resources. The first resource has a capacity of 1 . 7 loans per minute. The capacity of

Loans are evaluated in a process with two resources. The first resource has a capacity of 1.7 loans per minute. The capacity of the second resource is 2.3 loans per minute. Demand for this process is 1.4 loans per minute.
What is the cycle time of this process (in seconds)?
Note: Do not round intermediate calculations. Round your answer to 3 decimal places.
Cycle time (in seconds)