Question: Match each basic Process Group to the Project Schedule Management process that occurs within the group. Not all Process Groups will be used and some
Match each basic Process Group to the Project Schedule Management process that occurs within the group. Not all Process Groups will be used and some Process Groups will be used more than once.
Plan Schedule Management | Answer 1 Choose...1.Initiation 2.Closing 3.Planning. 4.Execution. 5.Monitoring and Controlling |
Define Activities and Sequence Activities | Answer 2 Choose... 1.Initiation 2.Closing 3.Planning 4.Execution. 5.Monitoring and Controlling |
Estimate Activity Durations | Answer 3 Choose... 1.Initiation 2.Closing 3.Planning 4.Execution. 5.Monitoring and Controlling |
Develop Schedule | Answer 4 Choose... 1. Initiation 2.Closing 3.Planning 4.Execution 5.Monitoring and Controlling |
Control Schedule | Answer 5 |
|
Choose... 1. Initiation 2.Closing 3.Planning 4.Execution 5.Monitoring and Controlling |