Question: Material Requirements Planning Exercise Learning Objective : The purpose of this exercise is to demonstrate the materials requirement planning (MRP) functionality. As a first step,

Material Requirements Planning Exercise

Learning Objective: The purpose of this exercise is to demonstrate the materials requirement planning (MRP) functionality. As a first step, a small test problem with five materials in a BOM is solved manually to determine planned order releases by carrying out MRP calculations. The problem is solved in a traditional way with weekly time buckets.

Calculate Planned Order Releases for materials A-XXX (YOUR LEARN ###), B-XXX (YOUR LEARN ###), C-XXX (YOUR LEARN ###), D-XXX (YOUR LEARN ###), and E-XXX (YOUR LEARN ###). Relevant data on independent requirements (forecast), BOM, and material master data are given below.

The BOM for product A-XXX is shown below. One piece of D-XXX and two pieces of E-XXX are assembled to make one unit of C-XXX. Two pieces of C-XXX and one piece of D-XXX are needed to make one subassembly of B-XXX. Four units of B-XXX are further assembled to make one unit of the product A-XXX.

Material Requirements Planning Exercise Learning Objective: The purpose of this exercise is

Independent requirements (demand) for product A-XXX (YOUR LEARN ###) are given below:

Period

Independent

Requirements

Week 49/Current year

60

Week 50/Current year

40

Week 51/Current year

80

Week 52/Current year

100

Some Relevant Material Master Data

Material

Lot Size

Lead time

Procurement type

Remarks

A-XXX

LFL

5 days (1 Week)

In-house production

Finished Product

B-XXX

LFL

5 days (1 Week)

In-house production

Semi-finished Product

C-XXX

LFL

10 days (2 Week)

In-house production

Semi-finished Product

D-XXX

Fixed Lot of 300

5 days (1 Week)

External Procurement

Raw Material

E-XXX

Fixed Lot of 500

5 days (1 Week)

External Procurement

Raw Material

NOTE: Lot Size

EX (in SAP) Lot-for-lot (LFL) is a lot sizing technique, where orders produced are the exact amount needed. In a materials requirement planning (MRP) environment, lot size is equal to the net requirements for that period.

FX (in SAP) fixed lot size which is always uses the same quantity (or a multiple) for a reorder

to demonstrate the materials requirement planning (MRP) functionality. As a first step,

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!