Question: MS Project Problem - Suppose we have a complete activity predecessor table (shown below). Using MS roject, enter the activities, their durations and predecessors (use

MS Project Problem - Suppose we have a completeMS Project Problem - Suppose we have a complete

MS Project Problem - Suppose we have a complete activity predecessor table (shown below). Using MS roject, enter the activities, their durations and predecessors (use default Fixed Units). 9. Assume Activity B takes 7 days as stated in the previous question. Activities A through I are now 100% complete. What is the total project percent complete? A) 42% B) 46% C) 53% D) 57%