Question: Multiple Choice A project manager is Considering how to structure a project tearn that will not directly desrupt ongoirig operations. The project needs to bedone

Multiple Choice
A project manager is Considering how to structure a project tearn that will not directly desrupt ongoirig operations. The project needs to bedone quickly and a high level of motivation will be needed in order to do that. For this situation, thebest choice.
projectized
strong matrix
weak matrix
Help
functional
Seve & Exit Submit
organtzation wOuld be the