Question: QUESTION 5 Given the following information, please answer question 5 to question 8 Activity Immediate Predecessors Completion Time ( Weeks ) A N / A
QUESTION
Given the following information, please answer question to question
Activity
Immediate Predecessors
Completion Time Weeks
A
NA
B
A
C
A
D
B
E
BC
F
D
G
E
H
E
Q What are the latest start and the latest finish of the activity E
Oa
b
c
Od
If activity B was delayed weeks, what is the new total project completion time?
Group of answer choices
What is the critical path?
Group of answer choices
A B C H
A C E H
A C E G
A B D F
What is the total project completion time?