Question: n electronics manufacturer makes remote control devices for interactive - cable - TV systems. The following assembly tasks must be performed on each device. Task
n electronics manufacturer makes remote control devices for interactivecableTV systems. The following assembly tasks must be performed on each device.
Task
Description
Predecessors
Time min
A
Place circuit into circuit frame
B
Solder circuit connections to central circuit control
A
C
Place circuit assembly in device frame
B
D
Attach circuit assembly to device frame
C
E
Place and attach display to frame
F
Place and attach keypad to frame
G
Place and attach top body of device to frame
E F
H
Place and attach battery holder to frame
D
I
Place and attach bottom body of device to frame
G H
J
Test device
I
Draw the precedence diagram for this problem, then determine the following:
a What is the sum of the task times?
Select
minutes
b What cycle time will allow the production of units over a tenhour day?
Select
minutes
c What is the theoretical number of workstations needed?
Select
d Balance this assembly line using the heuristic longest operation time, what is the actual number of stations?
Select
e What is the efficiency based on your answer to letter d
Select
f How much idle time is in this process based on the longest operation time?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock