Question: N N N B Using the information given, calculate the replenishment time when no beginning inventory exists. Immediate Leed Time Component Parent (weeks) A 4

N N N B Using the information given, calculate

N N N B Using the information given, calculate the replenishment time when no beginning inventory exists. Immediate Leed Time Component Parent (weeks) A 4 B 3 D 4 E A F B G 1 H D 3 D 3 J 8 K E 1 L E 4 F 4 4 o 2 P K 2 K 2 - NNN A D G H ! K L M N 0 P The cumulative lead time, the longest planned length of time to complete the end product, is weeks