Question: Using the information given, calculate the replenishment time when no beginning inventory exists. Component Immediate Parent Leed Time (weeks) A - 3 B A 3
Using the information given, calculate the replenishment time when no beginning inventory exists.
| Component | Immediate Parent | Leed Time (weeks) |
|---|---|---|
| A | - | 3 |
| B | A | 3 |
| C | A | 6 |
| D | A | 3 |
| E | A | 1 |
| F | B | 1 |
| G | B | 2 |
| H | D | 1 |
| I | D | 4 |
| J | E | 6 |
| K | E | 4 |
| L | E | 2 |
| M | F | 1 |
| N | F | 4 |
| O | H | 3 |
| P | K | 4 |
| Q | K | 1 |
The cumulative lead time, the longest planned length of time to complete the end product, ____ weeks.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
