Question: Using the information given, calculate the replenishment time when no beginning inventory exists. Component Immediate Parent Leed Time (weeks) A - 3 B A 3

Using the information given, calculate the replenishment time when no beginning inventory exists.

Component

Immediate Parent

Leed Time (weeks)

A

- 3

B

A 3

C

A 6

D

A 3

E

A 1

F

B 1

G

B 2

H

D 1

I

D 4

J

E 6

K

E 4

L

E 2

M

F 1

N

F 4

O

H 3

P

K 4

Q

K 1

The cumulative lead time, the longest planned length of time to complete the end product, ____ weeks.