Question: Using the information given, calculate the replenishment time when no beginning inventory exists. Component Immediate Parent Leed Time (weeks) A - 4 B A 2
Using the information given, calculate the replenishment time when no beginning inventory exists.
Component Immediate Parent Leed Time (weeks)
A - 4
B A 2
C A 4
D A 4
E A 4
F B 2
G B 1
H D 3
I D 3
J E 8
K E 1
L E 2
M F 4
N F 4
O H 4
P K 4
Q K 1
A
B C D E
F G H I J K L
M N O P Q
The cumulative lead time, the longest planned length of time to complete the end product, is ???? weeks.