Question: Name: Task Dependencies Optimistic Pessimistic TE VAR STD Duration (days) 8 15 15 T2 6 13 19 14 T3 TI 16 11 8 T4 10

Name: Task Dependencies Optimistic Pessimistic TE
Name: Task Dependencies Optimistic Pessimistic TE VAR STD Duration (days) 8 15 15 T2 6 13 19 14 T3 TI 16 11 8 T4 10 15 TS 10 9 14 T6 3 10 T7 5 20 25 15 22 30 T8 23 T2, T4 TI, T2 14 T3, T6 T5, T6 T7.19 T11 T9 15 13 17 15 16 0 TI1 T12 11 5 9 7 10 9 14 1) Find out the CP by drawing the Network diagram (need to show ES, Duration.EF. LS, LF, Slack) 2) What is the probability to finish one day earlier 3) What is the probability to finish one day late