Question: Nume Task Dependencies Optimistic Pessimistic TE Duration (days) 8 VAR STD TI 6. 13 T2 14 15 15 T3 TI 11 19 16 15 T4

Nume Task Dependencies Optimistic Pessimistic TE

Nume Task Dependencies Optimistic Pessimistic TE Duration (days) 8 VAR STD TI 6. 13 T2 14 15 15 T3 TI 11 19 16 15 T4 10 & TS 10 9 14 TG 5 T2, T4 TI, T2 TI 3 10 17 22 20 25 15 23 TR T4 30 15 13 19 17 15 11 16 13. 16 TS. 16 17.19 T T10 T11 TI2 9 5 7 9 10 1) l'ind out the CP by dowing the Network diagram (need to show ES, Duration: LS, LF. Slack) 2) What is the probability to linish one day earlier 3) What is the probability to finish one day late