Question: Name: Task Duration (days) 8 Dependencies Optimistic Pessimistic TE VAR STD TI 6 T2 14 15 15 T3 13 19 16 15 11 10 8

Name: Task Duration (days) 8 Dependencies
Name: Task Duration (days) 8 Dependencies Optimistic Pessimistic TE VAR STD TI 6 T2 14 15 15 T3 13 19 16 15 11 10 8 T4 T5 T6 10 14 9 3 5 10 T2, T4 T1, T2 TI T4 T7 20 15 22 T8 25 23 30 15 13 15 11 T9 T10 TI1 T12 T3, TO T5, T6 17,79 TIL 17 16 9 14 5 7 10 9 1) Find out the CP by drawing the Network diagram (need to show ES. Duration.EE, LS, LF. Slack) 2) What is the probability to finish one day earlier 3) What is the probability to finish one day lats