Question: Task TE Dependencies Optimistic Pessimistic Duration (days) 8 VAR STD 6 13 T2 15 14 19 T3 15 11 16 T4 10 8 15 TS

Task TE Dependencies Optimistic Pessimistic

Task TE Dependencies Optimistic Pessimistic Duration (days) 8 VAR STD 6 13 T2 15 14 19 T3 15 11 16 T4 10 8 15 TS 10 9 14 T2, T4 T1, T2 T6 5 3 10 T7 20 15 22 T8 25 T4 23 30 T9 15 13 17 T10 15 T3, TO T5, T6 17,19 11 16 TIT 7 5 9 T12 10 TIT 9 14 1) Find out the CP by drawing the Network diagram (need to show ES, Duration.E.E. LS, LF, Slack) 2) What is the probability to finish one day earlier 3) What is the probability to finish one day late