Question: Naomi is working on a software project which has several modules that will be produced by different vendors. Naomi talked with the team leaders at

Naomi is working on a software project which has several modules that will be produced by different vendors. Naomi talked with the team leaders at each vendor and asked them to give her an estimate of how long it will take to do their respective tasks. Which tool and technique is Naomi using to estimate the activity duration and why?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Naomi is utilizing the Expert Judgement tool and technique to estimate the activity duration in h... View full answer