Question: Nikko is going to make some adjustments in her project plan by adding work contours. Which statement is true about work contours in Project?Select an
Nikko is going to make some adjustments in her project plan by adding work contours. Which statement is true about work contours in Project?Select an answer:The work contour column shows a workload is applied.They apply to assignments.The bell contour is the default.They only apply to manual scheduled tasks.