Question: No explanation just answer please Activity Immediate Predecessor Time in Days A None 5 B A 2 C A 7 D B and C 6

No explanation just answer please ActivityNo explanation just answer please

Activity Immediate Predecessor Time in Days A None 5 B A 2 C A 7 D B and C 6 E 12 F B 22 G A 4 H . D, E, F, G 10 The above table is a simple project listing 8 activities and their respective time estimates: Using the Single Time Estimate CPM procedure, what are all of the activities that are not on critical path? Select one: O CD OB, D, F, G O C,D,E, G O None of the choices display all activities that are not on critical path B, C, D, E