Question: Normal Immediate Time Activity Predecessors (weeks) A none 4 B A 4. B 10 D B 2 E 9 F D 10 G EF 5

Normal Immediate Time Activity Predecessors
Normal Immediate Time Activity Predecessors (weeks) A none 4 B A 4. B 10 D B 2 E 9 F D 10 G EF 5 Normal Cost ($) 3.000 5.000 2.000 3,000 4,000 4.000 2.000 Crash Time (weeks) 3 2 2 1 6 Crash Cost (S) 18,000 11,000 10,000 12.000 12,000 6,000 10.000 Maximum Weeks Reduced 1 2 8 1 Normal Immediate Time Activity Predecessors (weeks) A none 4 B A 4. B 10 D B 2 E 9 F D 10 G EF 5 Normal Cost ($) 3.000 5.000 2.000 3,000 4,000 4.000 2.000 Crash Time (weeks) 3 2 2 1 6 Crash Cost (S) 18,000 11,000 10,000 12.000 12,000 6,000 10.000 Maximum Weeks Reduced 1 2 8 1