Question: Note: If the image appears too small you can right click and open the image in a new tab to better see the given information!

Note: If the image appears too small you can right click and open the image in a new tab to better see the given information!
Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times: Immediate Predecessor(s) Time Activity (weeks) A 6 B 8 3 D 1 Activity E F Time (weeks) 4 6 10 6 Immediate Predecessor(s) B B C, E DF G A H Dave's earliest start (ES) and earliest finish (EF) are: ES EF Activity A 6 Enter your answer in the answer box and then click Check Answer. 25 parts Clear All Check Answer remaining
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts