What would improve the schedule? (Note: these are to be considered as separate possibilities and do not interact with each other)

1)Use a small amount of budget contingency to reduce task 6 to 2 weeks2)Use surplus resources to reduce tasks 2, 3 and 5 by one week.3)Use budget contingency to reduce tasks 1, 4, and 5 by one week.4)Use an outside supplier to reduce task 3 to 1 week, task 5 to 2 weeks and task 6 to 1 week without a budget impact