Question: onsider the following work breakdown structure: Time Estimates ( days ) Activity Precedes Optimistic Most Likely Pessimistic Start A , B , C - -

onsider the following work breakdown structure:
Time Estimates (days)
Activity Precedes Optimistic Most Likely Pessimistic
Start A,B,C ---
A D 385062
B E 9099108
C End 85100115
D F 192531
E End 91100115
F End 626568
What is the estimated expected (mean) time for activity E?