onsider the following work breakdown structure:
| Time Estimates (days) | ||||||||||
| Activity | Precedes | Optimistic | Most Likely | Pessimistic | ||||||
| Start | A,B | - | - | - | ||||||
| A | C,D | 44 | 50 | 56 | ||||||
| B | D | 45 | 60 | 75 | ||||||
| C | E | 42 | 45 | 48 | ||||||
| D | F | 31 | 40 | 49 | ||||||
| E | F | 27 | 36 | 39 | ||||||
| F | End | 58 | 70 | 82 | ||||||
What is the probability that the critical path for this project will be completed within 210 days?
Multiple Choice
-
0.9987
-
0.8413
-
0.9772
-
0.9544
-
0.5000