Question: onsider the following work breakdown structure: Time Estimates (days) Activity Precedes Optimistic Most Likely Pessimistic Start A,B - - - A C,D 44 50 56

onsider the following work breakdown structure:

Time Estimates (days)
Activity Precedes Optimistic Most Likely Pessimistic
Start A,B - - -
A C,D 44 50 56
B D 45 60 75
C E 42 45 48
D F 31 40 49
E F 27 36 39
F End 58 70 82

What is the probability that the critical path for this project will be completed within 210 days?

Multiple Choice

  • 0.9987

  • 0.8413

  • 0.9772

  • 0.9544

  • 0.5000