onsider the following work breakdown structure:
Duration Estimates (Days)
Activity Precedes Optimistic Most Likely Pessimistic
Start U,V ---
U W 355065
V W,X 284052
W Z 263544
X Y 284052
Y Z 262938
Z End 366084
What is the estimated slack time for activity W?