Question: onsider the following work breakdown structure: What is the estimated slack time for activity A ? a . 1 0 0 days b . 4

onsider the following work breakdown structure:
What is the estimated slack time for activity A?
a.
100 days
b.
40 days
c.
0 days
d.
60 days
e.
20 days