Question: onsider the following work breakdown structure: Start Finish Duration ( days ) Activity Node Node Optimistic Most Likely Pessimistic A 1 2 4 1 5

onsider the following work breakdown structure:
Start Finish Duration (days)
Activity Node Node Optimistic Most Likely Pessimistic
A 12415059
B 13546066
C 24587082
D 34324144
What is the estimated slack time for activity D?