Question: OUESTION 2 Suppose you are managing a software development project. The project is expected to be completed in 1 2 months at a cost of

OUESTION 2
Suppose you are managing a software development project. The project is expected to be
completed in 12 months at a cost of $6,000 per month. After 3 months, you realize that
the project is 30 percent completed at a cost of $30,000. Determine the following:
a. PV (Planned Value)
(4 Marks)
b. EV (Earned Value)
(4 Marks)
c. Status with regards to budget
(4 Marks)
d. Status with regards to schedule
(4 Marks)