Question: Overall Process Attributes Average demand: 5 2 0 / day Batch size: 3 0 Number of shifts per day: 3 Availability: 8 hours per shift

Overall Process Attributes
Average demand: 520/day
Batch size: 30
Number of shifts per day: 3
Availability: 8 hours per shift with a 45 minute lunch break
Process Step 1
Cutting
Cycle timeequals126 seconds
Setup timeequals4 minutes
Up timeequals100%
Operatorsequals1
WIPequals350 units(before Cutting)
Process Step 2
Bending
Cycle timeequals240 seconds
Setup timeequals7 minutes
Up timeequals90%
Operatorsequals2
WIPequals550 units(before Bending)
Process Step 3
Punching
Cycle timeequals130 seconds
Setup timeequalsnone
Up timeequals100%
Operatorsequals1
WIPequals250 units(Before Punching)
WIPequals1 comma 200 units(After Punching)
Supplier Information
One shipment of 2 comma 600 units each week
Information Flow
All communications with customer are electronic
There is a weekly order release to Cutting
All material i

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!