Question: P . 9 - 3 Given the following network and probabilistic activity time estimates, determine the expected time and variance for each activity and indicate

P.9-3 Given the following network and probabilistic activity time estimates, determine the expected time and variance for each activity and indicate the critical path: , Use only meantime (m) and conpute CMP
each activity and indicate the critical path
\table[[,Time Estimates (weeks)],[Activity,a,m,b],[1,6,10,15],[2,2,7,16],[3,4,8,11],[4,3,10,15],[5,7,9,20],[6,4,12,15],[7,3,6,9],[8,5,9,16],[9,3,20,35],[10,4,12,16],[11,2,9,14]]