Question: Given the following network and probabilistic activity time estimates, determine the expected time and variance for each activity and indicate the criticalpath: 4,12.1 14 Start
.png)
4,12.1 14 Start Finish 2,3,14 10 12,1 Time Estimates fweeks Activity 16 15 20 15 16 35 16 14 10
Step by Step Solution
3.39 Rating (158 Votes )
There are 3 Steps involved in it
Activity a m b t ES EF LS LF Slack 1 6 10 15 1016 0 101... View full answer
Get step-by-step solutions from verified subject matter experts
Document Format (1 attachment)
184-B-M-L-O-M (447).docx