Question: Part 1: AON Draw AON (Activity on Node) network. Indicate the critical path and the total duration of the project. Show ES, EF, LS, LF,
Part 1: AON
Draw AON (Activity on Node) network. Indicate the critical path and the total duration of the project. Show ES, EF, LS, LF, TF, FF for each task.
| Task | Duration (in days) | Predecessors |
| a | 0 | |
| b | 5 | a |
| c | 8 | b |
| d | 15 | b |
| e | 5 | j,i,d,c |
| f | 7 | e |
| g | 14 | e |
| h | 5 | a |
| i | 7 | h |
| j | 8 | h |
| k | 4 | f,g |
| l | 10 | k |
| m | 9 | l |
Draw with software such as MS Word, Visio or PowerPoint. You are not allowed to use scheduling software and are limited to a total of two pages. Do not hand in a hand-drawn paper or a picture of a hand-drawn paper.
Part 2: EVM
Youre working on the Office Building project. You are the project manager and creating a status report today. Today is the end of the 10th day. The project budget is estimated as $100,000. It has costed the project $100,000. Youve planned to finish $60,000 amount of work so far.
Calculate the followings, show calculation and provide conclusion statement in plain English.
1) Current Month, BAC, AC, PV, EV
2) AT, ST
3) CV, SV
4) TV
5) CPI, SPI, CSI
6) PC, Percent Overrun, Burn Rate
7) ETC, EAC, VAC
8) TCPI