Question: [ Part 1 of 2 ] Consider the network below with optimistic, pessimistic and most likely activity durations listed ( durations given in days )

[Part 1 of 2] Consider the network below with optimistic, pessimistic and most likely activity durations listed (durations given in days).
\table[[Activity,Optimistic,Most Likely,Pessimistic],[A,3,4,15],[B,2,3,9],[C,7,9,13],[D,10,11,14],[E,2,5,12],[F,2,5,9],[G,7,14,15],[H,4,9,14]]
All of the network paths are displayed in the table below. Determine the expected duration and variance of each of the paths, and indicate whether or not each path is critical. If there are only three paths, type -1 in the duration cell in fourth row of the answer table below, and select NA in the critical path column. State all durations and variances exactly (i.e. not as rounded decimals).
Path
Start ADF End
Start ADH End
Start BCG End
Start BEG End
Expected
Duration
q,
q,
q,
q,
Critical Path?
Variance
q,
q,
q,
 [Part 1 of 2] Consider the network below with optimistic, pessimistic

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!