Part 1. Project Management
The following graph gives task names and durations (in days) for a project.
Question 1
What is duration of the project?
A.22 days
B.15 days
C.20 days
D.21 days
E.28 days Question 2
Which is the critical path?
A.C-F-G
B.B-E-G
C.A-D-E-G
D.A-D-F-G
Question 3
What is the Earliest Start time for task G ?
A.16
B.0
C.15
D.22
E.25
Question 4
What is the Latest Finish time for task B?
A.13
B.0
C.3
D.6
E.12
Question 5
What is the Slack for task A?
A.1
B.0
C.4
D.6
E.9

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!