Question: Part 2: ( See figure 1 part 2 below ). Assume that activity A actually finished (duration) at 5 weeks, activity B actually finished (duration)

Part 2: (See figure 1 part 2 below). Assume that activity A actually finished (duration) at 5 weeks, activity B actually finished (duration) at 10 weeks, and activity C actually finished (duration) at 14 weeks. Can the project be completed in required completion time of 50 weeks? Why or why not? Which activities would you focus on to get the project back on schedule and why? (25 points)

Part 2: (See figure 1 part 2 below). Assume that activity A

Part 2: Table for Part 2

Activity # Activity ES EF LS LF Total Slack
1 A
2 B
3 C
4 D
5 E
6 F
7 G
8 H

EF=ES+ Estimated Duration LS = LF - Estimated Duration Required completion time =50 weeks =LF

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!