Question: Part 2: ( See figure 1 part 2 below ). Assume that activity A actually finished (duration) at 5 weeks, activity B actually finished (duration)
Part 2: (See figure 1 part 2 below). Assume that activity A actually finished (duration) at 5 weeks, activity B actually finished (duration) at 10 weeks, and activity C actually finished (duration) at 14 weeks. Can the project be completed in required completion time of 50 weeks? Why or why not? Which activities would you focus on to get the project back on schedule and why? (25 points)

Part 2: Table for Part 2
| Activity # | Activity | ES | EF | LS | LF | Total Slack |
| 1 | A | |||||
| 2 | B | |||||
| 3 | C | |||||
| 4 | D | |||||
| 5 | E | |||||
| 6 | F | |||||
| 7 | G | |||||
| 8 | H |
EF=ES+ Estimated Duration LS = LF - Estimated Duration Required completion time =50 weeks =LF