Question: Given a simple project illustrated in the following table Immediate Time Activity Predecessors(weeks) 1 2 2 1 3 3 1 2 4 2,3 5 5

Given a simple project illustrated in the
Given a simple project illustrated in the following table Immediate Time Activity Predecessors(weeks) 1 2 2 1 3 3 1 2 4 2,3 5 5 3 AN Assume that "Activity 1" actually finished at 2 weeks, "Activity 2" actually finished at 6 weeks, and "Activity 3" actually finished at 5 weeks. Given the actual project progress, what is the expected project completion time? 12 13 11 14