Question: Partial information about Project GX151 is given below. Activity G, 24 days, IP = not given Activity H, 37 days, IP = not given Activity

Partial information about Project GX151 is given

Partial information about Project GX151 is given below. Activity G, 24 days, IP = not given Activity H, 37 days, IP = not given Activity K, 26 days, IP = not given Activity M, 26 days, IP = G Activity N, 20 days, IP = G, H, K Activity P, 24 days, IP = K Activity Q, 13 days, IP = N Activity R, 15 days, IP = N, P A You also know the following: LF of M = 195, LF of Q = 231, LF of R = 150. What is LS of G = ? Type a value only