Question: Partial information about Project GX151 is given below. Activity G, 32 days, IP = not given Activity H, 27 days, IP = not given Activity

 Partial information about Project GX151 is given below. Activity G, 32

Partial information about Project GX151 is given below. Activity G, 32 days, IP = not given Activity H, 27 days, IP = not given Activity K, 28 days, IP = not given Activity M, 16 days, IP = G Activity N. 32 days, IP = G, H, K Activity P, 28 days, IP = K. Activity Q. 15 days, IP = N Activity R, 28 days, IP = N, P You also know the following: LF of M = 154, LF of Q = 248, LF of R = 154. What is LS of G = ? Type a value only

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!