Question: Please answer all letters. c. Problem 2 (10 points) Given the following network and activity time what are a. Activities on critical path? b. Project

Please answer all letters. c. Problem 2 (10

Please answer all letters.

c. Problem 2 (10 points) Given the following network and activity time what are a. Activities on critical path? b. Project completion time? Slack for activities D and F? The variance of critical path? The probability that the project will be completed in 27 days or less. Time Estimates (Days) Immediate Predecessors Activity m b . 5 17 d. e. G 5 B 7 10 13 C 3 5 7 7 A D 1 3 5 5 A . E 4 5 6 8C F 3 3 3 3 BC G 3 3 4 in DE

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!