Question: Problem Problem: 1 Given the following network and activity time estimates, determine earliest and latest activity times, slack, the expected project completion time and variance,

Problem Problem:
1
Given the following network and activity time estimates, determine earliest and latest activity times, slack, the expected project completion time and variance, and the probability that the project will be completed in
2
8
days or less.
\
table
[
[
,
Time Estimates
(
Days
)
]
,
[
Activity
,
a
,
m
,
b
]
,
[
1
,
5
,
8
,
1
7
]
,
[
2
,
7
,
1
0
,
1
3
]
,
[
3
,
3
,
5
,
7
]
,
[
4
,
1
,
3
,
5
]
,
[
5
,
4
,
6
,
8
]
,
[
6
,
3
,
3
,
3
]
,
[
7
,
3
,
4
,
5
]
]
IRmAReglem determine the expected time and variance for each activity and indicate the critical path:
\
table
[
[
,
Time Estimates
(
weeks
)
]
,
[
Activity
,
a
,
,

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!