Question: Problem 2 (10 points) Given the following network and activity time, what are: Activities on critical path? b. Project completion time? Slack for activities D

Problem 2 (10 points) Given the following network
Problem 2 (10 points) Given the following network and activity time, what are: Activities on critical path? b. Project completion time? Slack for activities D and F? a. C. d. e. The variance of critical path? The probability that the project will be completed in 27 days or less. Time Estimates (Days) Immediate Predecessors Activity a m b A 5 8 17 7 10 13 C 3 5 7 D 1 3 5 E 4 6 8 B, C F 3 3 3 , G 3 4 5 D, E 543803&cmid23450418 page 1 BE III @