Question: please answer as soon as possible! it is urgent Schedule Varience, Cost Varience and EAC of Week 14 is * Cumulative Cost, in Thousands Variances
Schedule Varience, Cost Varience and EAC of Week 14 is * Cumulative Cost, in Thousands Variances Week BCWS BCWP ACWP Schedule EAC Cost 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 50 70 90 120 130 140 165 200 250 270 300 350 380 420 460 50 60 80 105 120 135 150 175 220 260 295 340 360 395 460 25 40 67 90 115 130 155 190 230 270 305 340 370 400 450 Your