Question: Please answer asap Using the information in the table below, assuming that the project team will work a standard working week (5 working days in
Using the information in the table below, assuming that the project team will work a standard working week (5 working days in 1 week) and that all tasks will start as soon as possible. Draw the project network diagram. What is the planned duration of the project in weeks? Identify the critical path of the project