Question: Please calculate ES, EF, LS & LF, CRITICAL PATH METHOD, Total slack time for below: For the network diagram, please not all the activities in
Please calculate ES, EF, LS & LF, CRITICAL PATH METHOD, Total slack time for below:
For the network diagram, please not all the activities in straight line Like A - B -C -D -E -F -G -H - I -J means later activity cannot start until preceding one is finished
Please show the steps how you reached the calculation.