Question: Please calculate ES, EF, LS & LF, CRITICAL PATH METHOD, Total slack time for below. Please calculate in how many days project will be finished.
Please calculate ES, EF, LS & LF, CRITICAL PATH METHOD, Total slack time for below. Please calculate in how many days project will be finished.
If project is not finished in 14 days then draw other activity chart and show calculations so the project can be completed with in 14days.
| WBS Number | Activity | Estimated duration in no. of days |
| A | Define Project | 1 |
| B | Meet with Homeowner | 1 |
| C | Meet with team to discuss | 1 |
| D | Report | 2 |
| E | Home Design | 1 |
| F | Design building plan | 1 |
| G | Report | 2 |
| H | Building Requirements | 1 |
| I | Compile all municipality requirements | 1 |
| J | Compile all other required clearances | 2 |
| K | Report | 2 |
| L | Project completion | 2 |
| M | Gather all documents for building plan | 1 |
| N | Report to Homeowners on all Building Plan requirements | 1 |
For the network diagram, please see below picture
Please show the steps how you reached the calculation
.