Question: Please calculate ES, EF, LS & LF, CRITICAL PATH METHOD, Total slack time for below: WBS Number Activity Estimated duration in no. of days A
Please calculate ES, EF, LS & LF, CRITICAL PATH METHOD, Total slack time for below:
| WBS Number | Activity | Estimated duration in no. of days |
| A | Define Project | 1 |
| B | Meet with Homeowner | 1 |
| C | Meet with team to discuss | 1 |
| D | Report | 2 |
| E | Home Design | 1 |
| F | Design building plan | 1 |
| G | Report | 2 |
| H | Building Requirements | 1 |
| I | Compile all municipality requirements | 1 |
| J | Compile all other required clearances | 2 |
| K | Report | 2 |
| L | Project completion | 2 |
| M | Gather all documents for building plan | 1 |
| N | Report to Homeowners on all Building Plan requirements | 1 |
For the network diagram, please see below picture
Please show the steps how you reached the calculation
.