Question: Please consider the following CPM activity-on-node diagram. The legend for this looks as follows: Early Start Duration Early Finish Analyze Requirements Late Start Slack/Buffer Late


Please consider the following CPM activity-on-node diagram. The legend for this looks as follows: Early Start Duration Early Finish Analyze Requirements Late Start Slack/Buffer Late Finish Please complete the diagram and answer the questions below. 0 3 6 5 5 Analyze Requirements Develop Code Test Code Cutover/Migration 4 4 2 Create Marketing Material Manage Change Celebrate Success What is the early finish of "Celebrate Success"