Question: Please do not assume any value Calculate % complete from this data. The project is expected to add 6 new features. The projected cost for

Please do not assume any value

Calculate % complete from this data.

The project is expected to add 6 new features. The projected cost for the project is $400,000 and my development time is 12 months. At the end of month 4 we spent $70,000 per feature and completed the development of two new features. The team is about to start the development of the third new software feature.

Requirement::

Calculate the Earned Value from the given data..

i need this answer asap..

Thanks.