Question: Please explain the process--I'm really confused how to even approach this question The following activities are part of a project to be scheduled using CPM:

Please explain the process--I'm really confused how to even approach this question
The following activities are part of a project to be scheduled using CPM: ACTIVITY A B IMMEDIATE PREDECESSOR TIME (WEEKS) 5 A 8 A 2 4 B%media:cm.png% D 5 D 4 E%media:cm.png F 8 D E F a. What is the critical path? O A-C-D-E-G OA-C-D-F-G O A-B-D-F-G O A-B-E-G b. How many weeks will it take to complete the project? Number of weeks c. How much slack does activity B have? Slack of activity weeksStep by Step Solution