Question: Please explain to me how to do the m by Hand and in MS Project. Construction Project management Problem 1 Task Days Predecessor 1 2
Please explain to me how to do the m by Hand and in MS Project. Construction Project management
Problem 1
| Task | Days | Predecessor |
| 1 | 2 days |
|
| 2 | 5 days | 1 |
| 3 | 6 days | 1 |
| 4 | 10 days | 3 |
| 5 | 8 days | 2,4 |
| 6 | 7 days | 3 |
| 7 | 6 days | 6 |
| 8 | 4 days | 5,7 |
| 9 | 4 days | 5 |
| 10 | 8 days | 8,9 |
Problem 2
| Task | Days | Predecessor |
| 1 | 2 days |
|
| 2 | 5 days | 1 |
| 3 | 6 days | 1 |
| 4 | 11 days | 3 |
| 5 | 9 days | 3 |
| 6 | 10 days | 5 |
| 7 | 10 days | 2,6,4 |
| 8 | 7 days | 3 |
| 9 | 6 days | 8 |
| 10 | 4 days | 7,9 |
| 11 | 4 days | 7 |
| 12 | 8 days | 10,11 |
Problem 3
| Task | Days | Predecessor |
| 1 | 5 days |
|
| 2 | 8 days | 1 |
| 3 | 6 days | 1 |
| 4 | 15 days | 3 |
| 5 | 12 days | 3 |
| 6 | 10 days | 5 |
| 7 | 8 days | 2,6,4,9 |
| 8 | 11 days | 3 |
| 9 | 7 days | 8 |
| 10 | 8 days | 7 |
| 11 | 4 days | 7 |
| 12 | 2 days | 10,11 |
Problem 4
| Task | Days | Predecessor |
| 1 | 2 days |
|
| 2 | 5 days | 1 |
| 3 | 6 days | 1 |
| 4 | 11 days | 3 |
| 5 | 12 days | 3 |
| 6 | 10 days | 5 |
| 7 | 8 days | 2,6,4,15 |
| 8 | 9 days | 3 |
| 9 | 7 days | 8 |
| 10 | 2 days | 7 |
| 11 | 4 days | 7,16 |
| 12 | 2 days | 10,11,19 |
| 13 | 7 days | 3 |
| 14 | 8 days | 13 |
| 15 | 5 days | 9 |
| 16 | 14 days | 3,8 |
| 17 | 7 days | 1 |
| 18 | 4 days | 17 |
| 19 | 2 days | 18 |
Problem 5
| Task | Days | Predecessor |
| 1 | 2 days |
|
| 2 | 5 days | 1 |
| 3 | 6 days | 1 |
| 4 | 10 days | 3 |
| 5 | 8 days | 2,4 |
| 6 | 11 days | 3 |
| 7 | 3 days | 6 |
| 8 | 4 days | 5,7 |
| 9 | 9 days | 5 |
| 10 | 7 days | 8,9 |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts