Question: Please explain to me how to do the m by Hand and in MS Project. Construction Project management Problem 1 Task Days Predecessor 1 2

Please explain to me how to do the m by Hand and in MS Project. Construction Project management

Problem 1

Task

Days

Predecessor

1

2 days

2

5 days

1

3

6 days

1

4

10 days

3

5

8 days

2,4

6

7 days

3

7

6 days

6

8

4 days

5,7

9

4 days

5

10

8 days

8,9

Problem 2

Task

Days

Predecessor

1

2 days

2

5 days

1

3

6 days

1

4

11 days

3

5

9 days

3

6

10 days

5

7

10 days

2,6,4

8

7 days

3

9

6 days

8

10

4 days

7,9

11

4 days

7

12

8 days

10,11

Problem 3

Task

Days

Predecessor

1

5 days

2

8 days

1

3

6 days

1

4

15 days

3

5

12 days

3

6

10 days

5

7

8 days

2,6,4,9

8

11 days

3

9

7 days

8

10

8 days

7

11

4 days

7

12

2 days

10,11

Problem 4

Task

Days

Predecessor

1

2 days

2

5 days

1

3

6 days

1

4

11 days

3

5

12 days

3

6

10 days

5

7

8 days

2,6,4,15

8

9 days

3

9

7 days

8

10

2 days

7

11

4 days

7,16

12

2 days

10,11,19

13

7 days

3

14

8 days

13

15

5 days

9

16

14 days

3,8

17

7 days

1

18

4 days

17

19

2 days

18

Problem 5

Task

Days

Predecessor

1

2 days

2

5 days

1

3

6 days

1

4

10 days

3

5

8 days

2,4

6

11 days

3

7

3 days

6

8

4 days

5,7

9

9 days

5

10

7 days

8,9

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!