Question: Please fill the blanks. given data activitiy predecesors duration (days) A - 4 B - 8 C A 12 D A 7 E B 6
Please fill the blanks.
given data
| activitiy | predecesors | duration (days) |
| A | - | 4 |
| B | - | 8 |
| C | A | 12 |
| D | A | 7 |
| E | B | 6 |
| F | C | 5 |
| G | C, E | 11 |
| H | D, F | 4 |
|
| EST | LST | EFT | LFT | TF | FF |
| A |
|
|
|
|
|
|
| B |
|
|
|
|
|
|
| C |
|
|
|
|
|
|
| D |
|
|
|
|
|
|
| E |
|
|
|
|
|
|
| F |
|
|
|
|
|
|
| G |
|
|
|
|
|
|
| H |
|
|
|
|
|
|
Find critical path, days and fill the all blanks. Thanks in advance!